    Brenner Base Tunnel opening delayed by two years

    The Brenner Base Tunnel will enter service in 2034, two years later than the previous target, with a whole-life cost of €11.73 billion. The announcement came on 21 October 2026 from BBT, the Italian-Austrian company building the tunnel, following the completion of the railway systems design and a review of the project timetable and costs. The final design dates back to 2008 and must now take account of technological developments and new safety regulations. Experience gained from the Gotthard Base Tunnel has also prompted a decision to convert the exploratory tunnel, the project's third tunnel, into a service tunnel. Much of the railway equipment originally intended for the two running tunnels will be relocated there. According to BBT, this will reduce exposure to dust and other risk factors, allowing most preventive maintenance to be carried out without disrupting rail traffic. Maintenance teams will be able to use road vehicles inside the service tunnel.

    Under BBT's revised timetable, construction will be completed in 2033, with testing, trial operations, statutory approvals and ancillary works not required for operation scheduled for 2034. The aim is to bring into service a system that complies with EU regulations and is coordinated between Italy and Austria. The project has also faced difficulties arising from differences between Italian and Austrian regulations, particularly concerning signalling and procurement procedures.

    The latest postponement follows a series of previous delays. Initial forecasts envisaged an opening between 2015 and 2016, and as late as 2005 the tunnel was still expected to enter service in 2015. In 2011, when the main construction phase began, the European Commission referred to completion by the end of 2025, while in 2019 the opening date was set for 2028. In May 2021, BBT's Supervisory Board acknowledged a delay caused by the suspension of work on the Pfons-Brenner construction lot following a dispute with the contractor consortium. It subsequently set 2031 as the target for completing construction, with operations beginning in 2032 in the best-case scenario and 2034 in the worst. Compared with the 2028 target announced in 2019, the opening has therefore slipped by six years.

    Costs have also risen steadily, although the various estimates are not directly comparable because they use different reference years for prices and include different cost items. In 2009, an estimate put the cost at €6 billion at 2006 prices. In 2011, the European Commission reported an agreed total cost of €8 billion, including risk provisions. In 2019, BBT estimated the base cost at €7.8 billion at 2017 prices and the overall cost at €8.384 billion, including risks and projected price adjustments through to 2028. In 2023, the whole-life cost was revised to €10.5 billion, comprising €8.54 billion in base costs, including railway systems, €1.092 billion in risk provisions and €903 million for anticipated inflation adjustments. In August, the Cipess (Interministerial Committee for Economic Planning and Sustainable Development) approved a spending ceiling of approximately €10.5 billion, of which around €5.3 billion was attributable to Italy. The €11.73 billion estimate announced in October exceeds that ceiling by approximately €1.2 billion. BBT's press release attributes the increase to three factors: modifications to the civil engineering works to accommodate the service tunnel and the extended construction timetable, railway systems upgrades required by new safety regulations, and inflation.

    Antonio Illariuzzi

    © TrasportoEuropa - Riproduzione riservata - Foto di repertorio
    Segnalazioni, informazioni, comunicati, nonché rettifiche o precisazioni sugli articoli pubblicati vanno inviate a: redazione@trasportoeuropa.it


      Puoi commentare questo articolo nella pagina Facebook di TrasportoEuropa

      bottone newsletter piccolo Vuoi rimanere aggiornato sulle ultime novità sul trasporto e la logistica e non perderti neanche una notizia di TrasportoEuropa? Iscriviti alla nostra Newsletter con l'elenco ed i link di tutti gli articoli pubblicati nei giorni precedenti l'invio. Gratuita e NO SPAM!

     

     

    CONTENUTI SPONSORIZZATI

     

Videocast K44

Aereo

  • Lufthansa Cargo estende la rete in Asia

    Lufthansa Cargo estende la rete in Asia

    Con l'orario invernale in vigore dal 25 ottobre 2026 Lufthansa Cargo opera 88 rotte con aerei cargo verso 40 destinazioni, aggiunge Singapore e ripristina Almaty. A Mumbai i voli tutto merci passano al nuovo aeroporto di Navi Mumbai, mentre crescono le frequenze verso Dallas, Houston e New York.

Ferrovia

  • L’apertura della galleria del Brennero rinviata di due anni

    L’apertura della galleria del Brennero rinviata di due anni

    Bbt sposta dal 2032 al 2034 la messa in esercizio della Galleria di base del Brennero e porta a 11,73 miliardi di euro il costo a vita intera. La riprogettazione dell'attrezzaggio ferroviario trasferisce gran parte degli impianti nel cunicolo esplorativo, trasformato in galleria di servizio.

Persone

  • Pessina confermato presidente di Federagenti

    Pessina confermato presidente di Federagenti

    L'Assemblea di Federagenti ha rinnovato all'unanimità la presidenza di Paolo Pessina, alla guida della federazione degli agenti marittimi dall'ottobre 2024. Ha indicato come fronti aperti le crisi geopolitiche che pesano sui porti e la riforma portuale.
Nuova generazione di carrelli automatici Toyota

TECNICA

Nuova generazione di carrelli automatici Toyota
previous arrow
next arrow
Amazon investe 16 miliardi in Germania, anche per la logistica

LOGISTICA

Amazon investe 16 miliardi in Germania, anche per la logistica
previous arrow
next arrow
Tre società indagate a Genova per frode sui carburanti

ENERGIE

Tre società indagate a Genova per frode sui carburanti
previous arrow
next arrow
CargoAi collega strategia aziendale e prenotazioni

SERVIZI

CargoAi collega strategia aziendale e prenotazioni
previous arrow
next arrow