Array ( [0] => 8 [1] => 39 )

Podcast K44

Cronaca

  • Multa di 6.000 euro per una bisarca polacca a Monfalcone

    Multa di 6.000 euro per una bisarca polacca a Monfalcone

    A Monfalcone la Polizia Locale ha multato con oltre seimila euro l’autista di una bisarca immatricolata in Polonia dopo un'analisi retrospettiva dei dati tachigrafici su 56 giorni, in cui ha rilevato diverse violazioni dei tempi di guida e riposo.

Transpotalk

Normativa

Mare

Autotrasporto

    After the Koralbahn, the Semmering tunnel will open in 2029

    Three railway base tunnels are currently at an advanced stage of construction in Europe: the Mont Cenis tunnel on the Turin-Lyon line, the Brenner tunnel and the Semmering tunnel between Lower Austria and Styria, on the Vienna-Graz route. But while forecasts for the completion of the first two tunnels continue to be pushed back, the countdown has officially begun for Semmering. The 27.3-kilometre Austrian tunnel will open for operations in December 2029, compared with the latest forecast, which had referred more generally to 2030. The schedule will therefore be met and, in fact, brought forward by a handful of months. Confirmation came directly from Austria’s mobility ministry and the chief executive of the federal railways ÖBB during a recent visit in which the tunnel was travelled through in full.

    Work on the twin-bore Semmering tunnel formally began on 25 April 2012 and will therefore be completed after almost 17 years of construction, now with a fixed date. To be objective, however, it should be remembered that the project has had a distinctly difficult path. Initial planning dates back to 1989, but mainly because of environmental concerns and difficulties with local stakeholders, time passed until 2005 without any outcome. At that point, the project was even abandoned. A new route was presented again in 2010, but here too there was no shortage of complications, including from a legal and administrative standpoint, with disagreements between the different Länder, until final approval came only in 2012.

    That brings us to recent developments. By the end of 2024, all excavation work on the two tunnel bores from Gloggnitz to Mürzzuschlag had been completed, and since summer 2025 the technical fit-out of the tunnels has been under way, including all the systems required for rail operations: track, power supply, signalling, safety and fire protection. The long timescales for this work should come as no surprise, as they are fully in line with those of comparable projects, such as the Gotthard base tunnel, which opened in 2016, although excavation had been completed between 2010 and 2011.

    With the opening of Semmering in 2029, one of the most demanding projects, with major positive effects for the entire Austrian rail network, will also be completed. The new base tunnel can be seen as a key piece completing the new high-capacity railway, at the heart of the TEN-T Baltic-Adriatic corridor, after the new Koralbahn entered service in December 2025. The 125-kilometre railway between Graz and Klagenfurt includes the 32.9-kilometre base tunnel beneath the Koralpe. In 100 days of operation, taking into account the November pre-opening reserved exclusively for freight traffic, the Koralbahn handled 1,000 cargo trains carrying more than one million tonnes of goods.

    The Semmering tunnel replaces the historic railway built in the mid-19th century by the Italian engineer Carlo Ghega, known in Austria by his adopted name Karl von Ghega. At the time, the line was considered a masterpiece of mountain railway engineering and is now a Unesco World Heritage site. Today, however, it is outdated and unsuitable for current traffic, especially freight, because of its steep gradients and tight-radius curves, as well as tunnels whose profile does not allow the passage of large-gauge intermodal trains.

    Piermario Curti Sacchi

    © TrasportoEuropa - Riproduzione riservata - Foto di repertorio
    Segnalazioni, informazioni, comunicati, nonché rettifiche o precisazioni sugli articoli pubblicati vanno inviate a: redazione@trasportoeuropa.it


      Puoi commentare questo articolo nella pagina Facebook di TrasportoEuropa

      bottone newsletter piccolo Vuoi rimanere aggiornato sulle ultime novità sul trasporto e la logistica e non perderti neanche una notizia di TrasportoEuropa? Iscriviti alla nostra Newsletter con l'elenco ed i link di tutti gli articoli pubblicati nei giorni precedenti l'invio. Gratuita e NO SPAM!

     

     

    CONTENUTI SPONSORIZZATI

     

Videocast K44

Aereo

  • Lufthansa Cargo cresce in aeroporto con Lug Aircargo Handling

    Lufthansa Cargo cresce in aeroporto con Lug Aircargo Handling

    Lufthansa Cargo ha annunciato a settembre 2026 un accordo per rilevare l’intero capitale di di Lug Aircargo Handling, società di movimentazione aeroportuale tedesca del gruppo Dettmer, ampliando la capacità nelle merci a supporto del piano di crescita del programma Lccevo.

Ferrovia

  • Il raccordo Orbassano-Avigliana nelle proteste No Tav

    Il raccordo Orbassano-Avigliana nelle proteste No Tav

    Si riaccende lo scontro tra le realtà locali per la realizzazione della ferrovia Torino-Lione. Ora la contestazione si sposta sulla tratta nazionale tra Torino Orbassano e Avigliana. Ma il commissario intende tirare dritto.

Persone

A Hannover debutto del camion elettrico Geely Farizon

TECNICA

A Hannover debutto del camion elettrico Geely Farizon
previous arrow
next arrow
Ceva sperimenta l’intralogistica automatica con minifurgoni

LOGISTICA

Ceva sperimenta l’intralogistica automatica con minifurgoni
previous arrow
next arrow
Tre arresti a Napoli per contrabbando di carburanti

ENERGIE

Tre arresti a Napoli per contrabbando di carburanti
previous arrow
next arrow
Nuove soluzioni Webfleet per flotte di camion

SERVIZI

Nuove soluzioni Webfleet per flotte di camion
previous arrow
next arrow