On 18 November 2026, the Slovenian government approved a bill providing a state guarantee for loans and debt securities worth up to €252.4 million. The guarantee will cover financing for the construction of the left-hand track on the new Divača–Koper railway, completing the double-track rail link to the Slovenian port. The bill now goes to the National Assembly under an urgent procedure, and the guarantee will take effect only after parliamentary approval. The Ministry of Infrastructure and Energy expects no direct impact on public finances, as the state would intervene only if 2TDK failed to meet its obligations. For the right-hand track, known as the "drugi tir", a 2019 law had already granted the same company a guarantee of up to €417 million.
The financing plan puts total funding requirements at €486.2 million. Guaranteed loans will cover more than half of this amount, with financing provided by the European Investment Bank and commercial banks. The plan also includes €190.3 million in non-repayable EU grants, which 2TDK intends to secure through calls for proposals under the 2028–2034 Multiannual Financial Framework, which is still being negotiated. The state has already contributed €43.5 million in equity through two instalments of €21.75 million, paid in 2025 and 2026. On 7 May 2026, the government, acting as the shareholders' meeting of 2TDK, authorised the second instalment and approved the investment programme.
In June 2026, 2TDK submitted its application for an integrated construction permit, while land acquisition and preparations for tenders are continuing. Construction is expected to begin in 2027 and be completed in 2030, partly because a substantial proportion of the underground infrastructure is already in place. The left-hand track will extend for 26.95 km, including 20.95 km through six tunnels. Three tunnel bores totalling 16.5 km have already been excavated as service tunnels for the right-hand track. Three further tunnels, with a combined length of approximately 4.5 km, remain to be built, along with the Gabrovica and Vinjan viaducts, measuring 1,060 metres in total, and the 64-metre bridge over the Glinščica.
With the new line, the railway route to the Port of Koper will be shortened from approximately 45 km to 26.95 km, while the maximum gradient will fall from 26 to 17 per mille. Trains up to 740 metres long will be able to operate on the route. Compared with the approximately 45 km of the historic alignment, the new route will reduce the distance to 26.95 km and the maximum gradient from 26 to 17 per mille, allowing 740-metre trains to run. On the existing line, which was declared congested by infrastructure manager SŽ-Infrastruktura in July 2018, 11.2 million net tonnes of freight were carried in 2024. During the same year, traffic averaged 89 trains per day, including 62 freight trains, while approximately 75% of services heading towards Divača required double-heading. With the double-track railway, capacity will increase from 212 to around 252 trains per day, allowing the historic alignment, which crosses a water protection area, to be taken out of service.
Antonio Illariuzzi