On 30 July 2025 the European Commission adopted a document referred to as an “implementing decision”, defining the deadlines and milestones for the construction of the new Turin–Lyon railway and setting out a strict timetable for every individual project that makes up the new high-capacity cross-border route between Italy and France. The document’s meaning, at least on paper, was clear: both countries must adhere rigorously to the schedule, a mandatory condition to secure the EU’s financial contributions to this major project included in the TEN-T network. EU resources would cover up to 55% of the cost of the base tunnel and up to 50% of the costs for the connecting lines in both countries.
But are these funds truly available and therefore spendable, or are they merely indicative commitments appearing in EU documents? The question is legitimate, particularly in light of a detailed analysis carried out by the Turin–Lyon technical commission set up by the Valle Susa Mountain Union. Although this analysis reflects a critical stance towards the project, it nonetheless deserves closer examination.
Beyond any consideration of the progress of the works and delays in implementation, the first issue is cost. Considering only the sections theoretically due for completion by 2033, the total cost of the Turin–Lyon project approaches €27 billion, including €14.7 billion for the base tunnel, the upgrading of existing lines in Italy and France, and the new national approach routes from Turin and Lyon. Costs are expected to rise further if the construction of the new rail bypass between Orbassano and Settimo Torinese is included—an infrastructure for which there is not even a preliminary design at present.
Is the European Union ready to open its wallet to guarantee its share of funding? A closer look at EU budgets is revealing. Since 2000, the Union has allocated €1.9 billion through TEN-T programmes up to 2013 and through CEF-Transport up to 2027. Overall, notes the Valle Susa Mountain Union commission, this represents around 12% of the current estimated cost of the base tunnel and less than 7% of all the interventions planned along the corridor up to 2033.
The underlying issue is the EU’s limited flexibility in releasing funds, as its financial programming is rigid and bound to budget cycles. The next cycle, covering the forthcoming CEF-T 2028–2034 programme, is to be defined over the next two years, with a financial allocation that already appears insufficient. It will likely require recourse to future funding under the 2042 programming cycle—or even the 2050 one.
In the previous funding round, Brussels allocated just €700 million for the construction of the Turin–Lyon base tunnel, suggesting that under CEF 2034 the project could receive at most around €2.3 billion—against a total requirement of €6.6 billion—and virtually nothing for the access lines on the Italian and French sides.
The European Commission’s “implementing decision” delivers another cold shower by stating that all additional financial burdens must be borne entirely by the national budgets of Italy and France, which have committed to covering all costs not financed by the EU or recouped through transit tolls. So far, Italy has pledged €5.6 billion, equivalent to 35% of the estimated cost of the base tunnel, while France’s share stands at a modest 12%. As for the national approach routes to the new Mont Cenis tunnel, the resources are even more limited—€900 million from Rome and €700 million from Paris. Given these premises, the game is still very much open.